32.
Commissioners Court Meeting
Meeting Date:
08/10/2026
Title:
CHANGE ORDER NO. 001 APPROVAL AND RATIFICATION FOR THE 1848 FAIRGROUNDS PAVILION & RESTAURANT RENOVATION PROJECT
Submitted for:
Martha Palacios
Submitted By:
Martha Palacios
Department:
Engineering

Subject:

Discussion and possible action to approve and ratify Change Order #001 in the amount of $623,013.51 to Leyendecker Construction of Texas Inc., for the Webb County 1848 Fairgrounds Pavilion & Restaurant Renovations Project; and have the County Judge sign any relevant documents and any other matters incident thereto.  [Account #3901-7230-001-474501 Capital-Buildings & Improvements-Site Work (Construction in Progress)]
 
Issue: The Change Order Items as requested by owner are as follows: Additional lighting package and electrical service upgrades, relocation of walls, doors and openings, plumbing revisions, relocation of fixtures, and an additional wood door at the new service counter at the Food Concession. HVAC system including equipment, ducts, air devices, labor, crane and startup. This will also include10% GC fee and a 1.2 % Bond cost.
 
Solution: Approval and ratification of change order #001.

Result: Proceed with project.

Background:

N/A

Previous Court Action:

N/A

Fiscal Impact

Budget Account Number:
0
Funding Source:
0
Balance:
0

Financial Impact:

3901-7230-001-474501 Capital-Buildings & Improvements-Site Work (Construction in Progress)