- Engineering Contract with Porras Nance Engineering for a Hydrologic & Hydraulic Study for San Carlos Phase I and Tanquecitos Colonias
- Submitted for:
- Nathan Bratton
- Submitted By:
- Nathan Bratton
- Department:
- Civil Legal Division
Subject:
Discussion and possible action to enter into an Engineering Contract with Porras Nance Engineering for a Hydrologic & Hydraulic Study for San Carlos Phase I and Tanquecitos Colonias in an amount not to exceed Four Hundred Ten Thousand Dollars ($410,000) and any matters incident thereto. [Fund #2703-5205 Revenue Replacement and authorizing additional funding $40,000 (original contract $370,000 to $410,000) from ARPA commitment]
Background:
H&H study is needed for flood control and prevention.
Previous Court Action:
Fiscal Impact
- Budget Account Number:
- ARPA
- Funding Source:
- unknown
- Balance:
- unknown
Financial Impact:
$410,000.00