30.
Commissioners Court Meeting
- Meeting Date:
- 02/10/2025
- Title:
- CHANGE ORDER FOR ARPA PROJECT NO. 0020-WEBB COUNTY RIO BRAVO DRAINAGE OUTFALL IMPROVEMENT PROJECT
- Submitted for:
- Martha Palacios
- Submitted By:
- Martha Palacios
- Department:
- Engineering
Subject:
Discussion and possible action to approve an additive Change Order (No. 1) to Gilmar Construction LTD., in the amount of $15,195.00 for Material Testing for ARPA Project No. 0020-Webb County Rio Bravo Drainage Outfall Rehabilition & Maintenance Improvement Poject; and have the County Judge sign any relevant documents; and any other matters incident thereto. [Account #2703-5205-001-474502-102 (Infrastructure in Progress-Rio Bravo North Ditch Repair)]
Issue: Material Testing is needed for quality control based on Contractor's preliminary plans.
Solution: The intent is to use part of the project contingency allowance to fund material testing.
Result: Quality control will be done on materials provided by the contractor.
Issue: Material Testing is needed for quality control based on Contractor's preliminary plans.
Solution: The intent is to use part of the project contingency allowance to fund material testing.
Result: Quality control will be done on materials provided by the contractor.
Background:
N/A
Previous Court Action:
N/A
Fiscal Impact
- Budget Account Number:
- 0
- Funding Source:
- 0
- Balance:
- 0
Financial Impact:
2703-5205-001-474502-102 Infrastructure in Progress-Rio Bravo North Ditch Repair