21.
Commissioners Court Meeting
- Meeting Date:
- 06/09/2025
- Title:
- APPROVAL OF CHANGE ORDER NO.3 FOR ADDITIONAL DAYS FOR ARPA PROJECT NO. 2-SOUTHERN FIRE STATION
- Submitted for:
- Martha Palacios
- Submitted By:
- Martha Palacios
- Department:
- Engineering
Subject:
Discussion and possible action to approve Change Order No. 3, Additional days for Quantcorp Construction LLC., for ARPA Project No. 2 - Webb County Southern Fire Station. The Contract Sum will not be increased by this Change Order; and authorize the Webb County Judge sign any relevant documents, and any other matters incident thereto. [No impact to the account]
Issue: There are items that have impacted the progress of the project, such as the delayed order for a custom-built water pump, the approval of changes for the fence to the septic tank, the air compressor's relocation and furnishing of equipment, and the installation of a water filtration system, the General Contractor requests that the current substantial completion date be extended Thirty (30) calendar days.
Solution: Approval of Change Order which will increase the contract time by thirty (30) days.
Result: Substantial completion date will be from June 9, 2025, to July 9, 2025.
Issue: There are items that have impacted the progress of the project, such as the delayed order for a custom-built water pump, the approval of changes for the fence to the septic tank, the air compressor's relocation and furnishing of equipment, and the installation of a water filtration system, the General Contractor requests that the current substantial completion date be extended Thirty (30) calendar days.
Solution: Approval of Change Order which will increase the contract time by thirty (30) days.
Result: Substantial completion date will be from June 9, 2025, to July 9, 2025.
Background:
N/A
Previous Court Action:
N/A
Fiscal Impact
- Budget Account Number:
- 0
- Funding Source:
- 0
- Balance:
- 0
Financial Impact:
NO IMPACT TO THE ACCOUNT