Subject:
Discussion and possible action to approve Change Order No. 4, additional days, for Quantcorp Construction LLC., for ARPA Project No. 0002-Southern Fire Station. The Contract Sum will not be increased by this Change Order; and authorize the Webb County Judge to sign any relevant documents; and any other matters incident thereto. [No Impact to the account]
Issue: The following items have impacted the progress of the project: AEP Texas power connection (15 days), and other approved changes: chain link gates at the generator area, water treatment system, shelves for the pantry area, wheel stops at the canopy area and fire lane additions (15 days), the General Contractor requests that the current substantial completion date to be extended thirty (30) calendar days.
Solution: Approval of Change Order which will increase the contract time by thirty (30) days.
Result: Substantial completion date will be from July 9, 2025, to August 9, 2025.
Issue: The following items have impacted the progress of the project: AEP Texas power connection (15 days), and other approved changes: chain link gates at the generator area, water treatment system, shelves for the pantry area, wheel stops at the canopy area and fire lane additions (15 days), the General Contractor requests that the current substantial completion date to be extended thirty (30) calendar days.
Solution: Approval of Change Order which will increase the contract time by thirty (30) days.
Result: Substantial completion date will be from July 9, 2025, to August 9, 2025.