15.b.
Commissioners Court Meeting
- Meeting Date:
- 07/14/2025
- Title:
- CHANGE ORDER FOR ADDITIONAL DAYS
- Submitted for:
- Martha Palacios
- Submitted By:
- Martha Palacios
- Department:
- Engineering
Subject:
Discussion and possible action to approve Change Order No. 1 Additional Days for Midas Contractors, LLC., for ARPA Project No. 0008-Webb County Community Action Agency Administration, Social Services & Meals on Wheels Project. The Contract Sum will not be increased by this Change Order; and authorize the Webb County Judge to sign any relevant documents; and any other matters incident thereto. [No impact to the account]
Issue: The following items have impacted the progress of the project:
Some of the listed items and other items are due to relocation and/or demolition due to remodeling. These and other items may be found on the attached documents. The completion date will be extended thirty (30) calendar days.
Solution: Approval of Change Order which will increase the contract time by thirty (30) days.
Result: Substantial completion date will be from September 21, 2025 to October 21, 2025.
Issue: The following items have impacted the progress of the project:
- Install furr wall to cover rough finish due to demolition of tile.
- Cut and cap a 6” water line that was found (not in plans) during the excavation of a storm drain line.
- Installation of carpet as requested by CAA in the Manager’s office.
- Ice maker relocation requested by CAA.
Some of the listed items and other items are due to relocation and/or demolition due to remodeling. These and other items may be found on the attached documents. The completion date will be extended thirty (30) calendar days.
Solution: Approval of Change Order which will increase the contract time by thirty (30) days.
Result: Substantial completion date will be from September 21, 2025 to October 21, 2025.
Background:
N/A
Previous Court Action:
N/A
Fiscal Impact
- Budget Account Number:
- 0
- Funding Source:
- 0
- Balance:
- 0
Financial Impact:
No Fiscal Impact