17.a.
Commissioners Court Meeting
- Meeting Date:
- 02/09/2026
- Title:
- APPROVAL OF CHANGE ORDER NO. 002 - ADDITIONAL DAYS FOR THE DEAN SENATOR J. ZAFFIRINI JUSTICE CENTER ROOF PROJECT
- Submitted for:
- Martha Palacios
- Submitted By:
- Martha Palacios
- Department:
- Engineering
Subject:
Discussion and possible action to approve Change Order No. 002 for Additional Days (30) Stoddard General Contractors for the Dean Senator Judith Zaffirini Justice Center Building Envelope Site Rehabilitation Project. The Contract Sum will not be increased by this Change Order; and authorize the Webb County Judge to sign any relevant documents; and any other matters incident thereto. [No Impact to the account]
Issue: The following items have impacted the progress of the project; Contingency Allowance CAA-004R and Contingency Allowance CA005R. These items may be found on the attached documents. Completion date to be extended thirty (30) calendar days.
Solution: Approval of Change Order which will increase the contract time by thirty (30) days.
Result: Substantial completion date will be July 30, 2026.
Issue: The following items have impacted the progress of the project; Contingency Allowance CAA-004R and Contingency Allowance CA005R. These items may be found on the attached documents. Completion date to be extended thirty (30) calendar days.
Solution: Approval of Change Order which will increase the contract time by thirty (30) days.
Result: Substantial completion date will be July 30, 2026.
Background:
N/A
Previous Court Action:
N/A
Fiscal Impact
- Budget Account Number:
- 0
- Funding Source:
- 0
- Balance:
- 0
Financial Impact:
No Impact to the account