25.
Commissioners Court Meeting
- Meeting Date:
- 05/26/2026
- Title:
- APPROVAL OF RESOLUTION FOR THE RELOCATION OF ARPA FUNDS
- Submitted for:
- Martha Palacios
- Submitted By:
- Martha Palacios
- Department:
- Engineering
Subject:
Discussion and possible action to approve a resolution for reallocating of Webb County’s ARPA Obligated Project Funds from One Project to Another. Webb County has appropriated all its ARPA allocated funds to 40 adopted projects meeting all requirements set forth by the State and Local Fiscal Recovery Funds (SLFRF) program guidelines. US Treasury under SLFRF Guidelines FAQ 17.16 allows for the transfer of Obligated ARPA Funds from project to project. Webb County authorizes Brighton Group to follow all SLFRF procedures in reporting with the US Treasury.
Issue: As per the project Engineers (ARDURRA Group) improvements are necessary to provide adequate pressure and flow, enhance system reliability, and meet both existing and future water demands for the La Presa Booster Pump Station Project. In addition, it supports the extension of the waterline from the Booster Pump Station to the La Presa community by ensuring adequate conveyance capacity, maintaining system pressures, and providing reliable and sustainable water service.
Solution: Webb County authorizes the movement of all ARPA Obligated funds from ARPA Project 0031 La Presa Ground Storage Tank Booster Station and assign to ARPA Project 0004 Waterline Extension Project which meets the requirements set forth and listed above.
Result: ARPA 0004 Waterline Extension Project will receive the additional Webb County ARPA funds to obligate them to address the need for adequate pressure by the installation of a Booster Pump Station within the scope of project. This will support the extension of the waterline from the Booster Pump Station to the La Presa community by ensuring adequate conveyance capacity, maintaining system pressures, and providing reliable and sustainable water service.
Issue: As per the project Engineers (ARDURRA Group) improvements are necessary to provide adequate pressure and flow, enhance system reliability, and meet both existing and future water demands for the La Presa Booster Pump Station Project. In addition, it supports the extension of the waterline from the Booster Pump Station to the La Presa community by ensuring adequate conveyance capacity, maintaining system pressures, and providing reliable and sustainable water service.
Solution: Webb County authorizes the movement of all ARPA Obligated funds from ARPA Project 0031 La Presa Ground Storage Tank Booster Station and assign to ARPA Project 0004 Waterline Extension Project which meets the requirements set forth and listed above.
Result: ARPA 0004 Waterline Extension Project will receive the additional Webb County ARPA funds to obligate them to address the need for adequate pressure by the installation of a Booster Pump Station within the scope of project. This will support the extension of the waterline from the Booster Pump Station to the La Presa community by ensuring adequate conveyance capacity, maintaining system pressures, and providing reliable and sustainable water service.
Background:
Webb County has received $53,736,408 it was allocated from the US Treasury American Rescue Plan Act (ARPA) State and Local Fiscal Recovery Funds (SLFRF). Webb County has provided additional funding through grants and other sources of funding to fulfill the approved and adopted ARPA Projects that are eligible under the American Rescue Plan Act Funds and approved by Webb County Commissioners Court.
A total of 40 Projects were developed and confirm that all funds were obligated by the Deadline of December 31, 2024. To date 27 projects have been fully completed while all remaining projects are coming to a final closing no later than December 31, 2026.
SLFRF Guidelines for surplus of Obligated Funds to Existing Projects is authorized by FAQ 17.16:
a.) Recipient may use SLFRF funds to cover increased costs attributable to pre-existing obligations to accommodate the change or contingency prior to December 31, 2024
b.) Recipients may also cover contract cost increases after December 31, 2024, using SLFRF funds that the recipient does not use as initially reported to cover projects.
c.) Recipients may cover cost of amendments to contracts if the amended contract is within substantially the same scope and for substantially the same purpose as the contract incurred by December 31, 2024.
Exhibit “A” identifies projects requiring additional funding.
A total of 40 Projects were developed and confirm that all funds were obligated by the Deadline of December 31, 2024. To date 27 projects have been fully completed while all remaining projects are coming to a final closing no later than December 31, 2026.
SLFRF Guidelines for surplus of Obligated Funds to Existing Projects is authorized by FAQ 17.16:
a.) Recipient may use SLFRF funds to cover increased costs attributable to pre-existing obligations to accommodate the change or contingency prior to December 31, 2024
b.) Recipients may also cover contract cost increases after December 31, 2024, using SLFRF funds that the recipient does not use as initially reported to cover projects.
c.) Recipients may cover cost of amendments to contracts if the amended contract is within substantially the same scope and for substantially the same purpose as the contract incurred by December 31, 2024.
Exhibit “A” identifies projects requiring additional funding.
Previous Court Action:
N/A
Fiscal Impact
- Budget Account Number:
- 0
- Funding Source:
- 0
- Balance:
- 0
Financial Impact:
No Impact