Discuss, consider and take appropriate action on Change Order No. 4, to the Agreement between Williamson County and J. T. Vaughn Construction, LLC, in the amount of $0 for Jacking and Boring for Roadway Sleeve in relation to the Williamson County North Campus Project.

Background

The original jack bore pit and man hole was in Oncor Electric’s right of way which they will not allow. This will move the pit and man hole approximately 85 feet so it will be out of Oncor’s right of way.

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Wendy Coco 04/26/2017 04:21 PM
Form Started By:
Gina Wrehsnig
Started On:
04/26/2017 02:51 PM
Final Approval Date:
04/26/2017