22.
Commissioners Court - Regular Session
- Meeting Date:
- 08/22/2017
- Title:
- 1604-068 Forest North Ph 1 Change Order No. 3
- Submitted By:
- Dawn Haggard, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take any appropriate action regarding Change Order No. 3 in the amount of $91,734.95 for Forest North Phase 1, a Road Bond Project in Commissioner Pct. 1.
Background
This Change Order compensates the Contractor for the removal of additional AC pipe by overrunning existing line items. This change was a request from the City of Austin (COA). The COA will also add quantity to the “CUT/RESTORE PAVEMENT FOR AC PIPE REMOVAL" item created in Change Order No. 2. This Change Order includes new line items for water services per the most recent COA water service detail, trench excavation protection for the additional AC pipe removal, reimbursements to Williamson County for a wastewater line adjustment and a water line construction delay, and a month of barricades to cover the additional amount of AC pipe removal. The City of Austin has agreed to compensate the Contractor for these costs.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Wendy Coco | 08/17/2017 11:02 AM |
- Form Started By:
- dhaggard
- Started On:
- 08/16/2017 10:44 AM
- Final Approval Date:
- 08/17/2017