32.
Commissioners Court - Regular Session
- Meeting Date:
- 12/12/2017
- Title:
- Georgetown Annex P325 - Change Order 3
- Submitted By:
- Gina Wrehsnig, Infrastructure
- Department:
- Infrastructure
- Division:
- Building Maintenance
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss and take appropriate action on Williamson County Georgetown Annex Project, P325, Change Order # 3 from Chasco Constructors, in the amount of $52,152.70 to increase the amount of pavement sub-grade lime stabilization treatment which is required to meet the original pavement design specifications. This change order is being funded out of the Owners Contingency.
Background
This change order is to reimburse the contractor for the cost of the additional lime material required to meet the original pavement design specifications for the project.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Wendy Coco | 12/07/2017 12:03 PM |
- Form Started By:
- Gina Wrehsnig
- Started On:
- 12/07/2017 10:36 AM
- Final Approval Date:
- 12/07/2017