Commissioners Court - Regular Session
- Meeting Date:
- 05/22/2018
- Title:
- Georgetown Annex P325 - Change Order 12
- Submitted By:
- Gina Wrehsnig, Infrastructure
- Department:
- Infrastructure
- Division:
- Building Maintenance
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider and take appropriate action on accepting and approving a report on the Georgetown Annex Project; Change Order # 12 in the amount of $7,623.00 to approve funding for the final exterior masonry stone selection, which was executed by Dale Butler, Williamson County Facilities Director, pursuant to the previous grant of authority under Section 262.031 of the Local Government Code. This change order is being funded by the Construction Managers Contingency.
Background
Final masonry stone pricing was not available until the final stone selection was made. This change order is to approve funding to cover the difference from the original estimate.
On September 6, 2016, the Williamson County Commissioners Court granted Dale Butler, Williamson County Facilities Project Manager, with general authority to approve change orders for the Agreement for Construction Services with Chasco Constructors, LTD, L.L.P. in relation to the Williamson County Georgetown Annex Project for any increase in costs up to a total maximum amount of $30,000.00 in accordance with Section 262.031 of the Local Government Code – Changes in Plans and Specifications. This report is being provided for purposes of notifying the court of such change order and to place it in the minutes of the Commissioners Court.
On September 6, 2016, the Williamson County Commissioners Court granted Dale Butler, Williamson County Facilities Project Manager, with general authority to approve change orders for the Agreement for Construction Services with Chasco Constructors, LTD, L.L.P. in relation to the Williamson County Georgetown Annex Project for any increase in costs up to a total maximum amount of $30,000.00 in accordance with Section 262.031 of the Local Government Code – Changes in Plans and Specifications. This report is being provided for purposes of notifying the court of such change order and to place it in the minutes of the Commissioners Court.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Wendy Coco | 05/17/2018 10:03 AM |
- Form Started By:
- Gina Wrehsnig
- Started On:
- 05/17/2018 09:26 AM
- Final Approval Date:
- 05/17/2018