20.
Commissioners Court - Regular Session
- Meeting Date:
- 06/05/2018
- Title:
- WCCHD Remodel P322; Change Order #25
- Submitted By:
- Gina Wrehsnig, Infrastructure
- Department:
- Infrastructure
- Division:
- Building Maintenance
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider and take appropriate action on the Texas Avenue Remodel Project, Change Order # 25 from Trimbuilt Construction, Inc., in the amount of $94,581.95 for exterior improvements, including waterproofing, joint sealant at all exterior wall joints, window sealant and re-coating of all exterior walls with fiber reinforced, elastomeric acrylic wall coating. This change order is being funded out of the Owners Contingency.
Background
This change order is being funded out of remaining project Owners Contingency funds. Re-coating the exterior of the building is necessary due to failing joint sealant at all siding and window joints. This scope of work was delayed until all other unknowns were funded during the regular project schedule.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Wendy Coco | 05/31/2018 10:16 AM |
- Form Started By:
- Gina Wrehsnig
- Started On:
- 05/31/2018 08:14 AM
- Final Approval Date:
- 05/31/2018