Title:
Animal Shelter Expansion, P435 - Change Order 4
Submitted By:
Gina Wrehsnig, Infrastructure
Department:
Infrastructure
Division:
Building Maintenance
Agenda Category:
Consent

Information

Agenda Item

iscuss, consider and take appropriate action on accepting and approving a report on the Regional Animal Shelter Expansion Project; Change Order # 4 in the amount of $10,554.00 to approve funding for additional plumbing and concrete scopes of work, which was executed by Dale Butler, Williamson County Facilities Director, pursuant to the previous grant of authority under Section 262.031 of the Local Government Code. This change order is being funded by the Construction Manager and Owner’s Contingencies.

Background

Change Order to fund additional concrete at transformer pad and for temporary animal care during the remodel process. This change order also funds additional plumbing scopes of work at surgery prep and pipe penetrations.
On August 15, 2017, the Williamson County Commissioners Court granted Dale Butler, Williamson County Facilities Director, with general authority to approve change orders for the Agreement for Construction Services with Vaughn Construction in relation to the Williamson County Regional Animal Shelter Expansion Project for any increase in costs up to a total maximum amount of $30,000.00 in accordance with Section 262.031 of the Local Government Code – Changes in Plans and Specifications. This report is being provided for purposes of notifying the court of such change order and to place it in the minutes of the Commissioners Court.

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Wendy Coco 07/19/2018 11:06 AM
Form Started By:
Gina Wrehsnig
Started On:
07/19/2018 10:27 AM
Final Approval Date:
07/19/2018