Discuss, consider, and take appropriate action regarding the Utility Agreement between Atmos Energy and Williamson County for utility relocations on North Mays Extension, a Road Bond Project in Commissioner Pct. 1.
Background
Atmos Energy has existing facilities which are in conflict with the proposed construction for the North Mays Extension Project. The reimbursement agreement allows them to relocate existing facilities (334 LF pipe) that are in conflict with the proposed roadway and install new facilities in the proposed right of way. The County will reimburse Atmos $93,665.31 for the installation of approximately 334 linear feet of gas pipeline. This relocation is 67.66% reimbursable. The total anticipated reimbursement to Atmos by the County is $93,665.31, which is 67.66% of the total eligible costs of $138,435.28. The total eligible costs do not include betterments, because those costs are paid for by the Utility Owner.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Wendy Coco | 11/08/2018 09:59 AM |
- Form Started By:
- dhaggard
- Started On:
- 11/06/2018 05:25 PM
- Final Approval Date:
- 11/08/2018