21.
Commissioners Court - Regular Session
- Meeting Date:
- 06/25/2019
- Title:
- Discuss consider and take appropriate action on approval of the preliminary plat for the Santa Rita Ranch South Section 16 subdivision – Pct 2
- Submitted For:
- Terron Evertson
- Submitted By:
- Adam Boatright, Infrastructure
- Department:
- Infrastructure
- Division:
- Road & Bridge
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider and take appropriate action on approval of the preliminary plat for the Santa Rita Ranch South Section 16 subdivision – Precinct 2.
Background
This proposed subdivision consists of 74 single family lots, 8 open space/drainage/utility/easement lots, a 200 foot wide reserve along SH 29 for future right-of-way and 2,176 feet of new public roads.
Timeline
2018-09-20 – Initial submittal of preliminary plat
2018-11-19 – 1st review complete with comments
2019-01-23 – 2nd submittal of preliminary plat
2019-03-12 – 2nd review complete with comments
2019-04-17 – 3rd submittal of preliminary plat
2019-06-11 – 3rd review complete with comments
2019-06-19 – 4th submittal of preliminary plat
2019-06-20 – 4th review complete with comments cleared
2019-06-20 – preliminary plat placed on June 25, 2019 Commissioners Court agenda for consideration
Timeline
2018-09-20 – Initial submittal of preliminary plat
2018-11-19 – 1st review complete with comments
2019-01-23 – 2nd submittal of preliminary plat
2019-03-12 – 2nd review complete with comments
2019-04-17 – 3rd submittal of preliminary plat
2019-06-11 – 3rd review complete with comments
2019-06-19 – 4th submittal of preliminary plat
2019-06-20 – 4th review complete with comments cleared
2019-06-20 – preliminary plat placed on June 25, 2019 Commissioners Court agenda for consideration
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Andrea Schiele | 06/20/2019 12:01 PM |
- Form Started By:
- Adam Boatright
- Started On:
- 06/20/2019 11:47 AM
- Final Approval Date:
- 06/20/2019