Commissioners Court - Regular Session
- Meeting Date:
- 12/17/2019
- Title:
- 1809-261 CR 110 Middle Change Order No. 2
- Submitted By:
- Dawn Haggard, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 2 in the amount of $31,881.14 for CR 110 Middle (James Construction Group) , a Road Bond project in Commissioner Pct. 4.
P:261 Funding Source: Road Bond
P:261 Funding Source: Road Bond
Background
This Change Order adds excavation and grading for the ditch line along the north side of Limmer Loop at CR 110. The construction of the ditch was originally included in the previous CR 110 South contract but was not completed due to a utility conflict. The underground utility was recently relocated, and the ditch excavation was added to the current project at the request of the County.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Andrea Schiele | 12/12/2019 10:09 AM |
- Form Started By:
- dhaggard
- Started On:
- 12/10/2019 02:04 PM
- Final Approval Date:
- 12/12/2019