44.
Commissioners Court - Regular Session
Meeting Date:
01/07/2020
Title:
North Campus Facilities P324 Vaughn Construction Change Order 71
Submitted For:
Dale Butler
Submitted By:
Wendy Danzoy, Building Maintenance
Department:
Facilities Management
Agenda Category:
Consent

Information

Agenda Item

Discuss, consider and take appropriate action on accepting and approving a report on the Williamson County North Campus Project; Change Order #71 in the amount of $0.00 to approve additional contract days, which was executed by Dwayne Gossett, Williamson County Facilities Project Manager, pursuant to the previous grant of authority under Section 262.031 of the Local Government Code.

Background

This change order is to add 130 contract days due to weather and VE/redesign days.
On September 6, 2016, the Williamson County Commissioners Court granted Dwayne Gossett, Williamson County Facilities Project Manager, with general authority to approve change orders for the Agreement for Construction Services with J. T. Vaughn Construction, LLC in relation to the Williamson County North Campus Project for any increase in costs up to a total maximum amount of $30,000.00 in accordance with Section 262.031 of the Local Government Code – Changes in Plans and Specifications. This report is being provided for purposes of notifying the court of such change order and to place it in the minutes of the Commissioners Court.

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Andrea Schiele 12/18/2019 09:56 AM
Form Started By:
wendy.danzoy
Started On:
12/17/2019 10:50 AM
Final Approval Date:
12/18/2019