42.
Commissioners Court - Regular Session
- Meeting Date:
- 01/28/2020
- Title:
- Discuss consider and take appropriate action on approval of the final plat for the Rancho Sienna Section 12B subdivision – Pct 3
- Submitted For:
- Terron Evertson
- Submitted By:
- Adam Boatright, Infrastructure
- Department:
- Infrastructure
- Division:
- Road & Bridge
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider and take appropriate action on approval of the final plat for the Rancho Sienna Section 12B subdivision – Precinct 3.
Background
This is the next section of the Rancho Sienna development. It consists of 67 single family lots, 2 open space lots, 1 open space/drainage lot and 2,425 feet of new public roads. Roadway and drainage construction is not yet complete, but a performance bond in the amount of $290,600.00 has been posted with the County to cover the cost of the remaining construction.
Timeline
2019-05-07 – initial submittal of the final plat
2019-05-31 – 1st review complete with comments
2019-06-27 – 2nd submittal of final plat
2019-08-27 – 2nd review complete with comments
2019-09-26 – 3rd submittal of final plat
2019-10-01 – 3rd review complete with comments
2019-11-04 – 4th submittal of final plat
2019-11-13 – 4th review complete with comments cleared except for remaining construction
2020-01-21 – receipt of performance bond for the cost of the remaining construction
2020-01-22 – receipt of final plat with all signatures
2020-01-23 – final plat placed on January 28, 2020 Commissioners Court agenda for consideration
Timeline
2019-05-07 – initial submittal of the final plat
2019-05-31 – 1st review complete with comments
2019-06-27 – 2nd submittal of final plat
2019-08-27 – 2nd review complete with comments
2019-09-26 – 3rd submittal of final plat
2019-10-01 – 3rd review complete with comments
2019-11-04 – 4th submittal of final plat
2019-11-13 – 4th review complete with comments cleared except for remaining construction
2020-01-21 – receipt of performance bond for the cost of the remaining construction
2020-01-22 – receipt of final plat with all signatures
2020-01-23 – final plat placed on January 28, 2020 Commissioners Court agenda for consideration
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Andrea Schiele | 01/23/2020 11:46 AM |
- Form Started By:
- Adam Boatright
- Started On:
- 01/23/2020 11:37 AM
- Final Approval Date:
- 01/23/2020