30.
Commissioners Court - Regular Session
- Meeting Date:
- 03/24/2020
- Title:
- 1811-278 - Forest North - Anderson Mill Change Order No. 2
- Submitted By:
- Dawn Haggard, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider and take appropriate action regarding Change Order No. 2 in the amount of $9,477.24 for the Forest North Anderson Mill (QA Construction), a Road Bond project in Commissioner Pct. 1.
P: 225 Funding: Road Bond
P: 225 Funding: Road Bond
Background
This Change Order adds the relocation to an existing City of Austin water service line. The existing line was discovered during construction and was in conflict with the installation of the new drainage system. The cost proposal from the Contractor was reviewed and approved by the City of Austin. The cost of this work will be paid by the City of Austin.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Andrea Schiele | 03/19/2020 10:00 AM |
- Form Started By:
- dhaggard
- Started On:
- 03/18/2020 10:16 AM
- Final Approval Date:
- 03/19/2020