1812-282 Seward Junction Improvements Change Order No. 6
Submitted By:
Dawn Haggard, Road Bond
Department:
Road Bond
Agenda Category:
Regular Agenda Items

Information

Agenda Item

Discuss, consider, and take appropriate action regarding Change Order No. 6 in the amount of $681.04 for the Seward Junction Improvements (Jordan Foster Construction), a Road Bond project in Commissioner Pct. 2.
P: 271 and 274  Funding Source: Road Bond

Background

This Change Order adds the latest TxDOT Guardrail End Treatment (MSKT) standard in the Contract, adds items for extending a storm sewer pipe, revises the slope for safety end treatments (SET) from 4:1 to 3:1 (RFI 28) and adds a pipe underdrain to address groundwater encountered during construction near the PEC Driveway (RFI 29).

The new TxDOT standard for the Guardrail End Treatment was updated and issued after the project was designed and will be implemented during construction.

The response to RFI 28 revised the profile grade line (PGL) of the proposed roadway from the south tie-in to the existing CR 266. Due to the change in the PGL, side slopes changed which required changes to Structure "I". Field changes include changes for two (2) SET's from 4:1 to 3:1 and an extension to the length of the storm sewer pipe.

The response to RFI 29 required the installation of an underdrain to allow runoff for groundwater encountered during construction and to stabilize the roadway foundation. The work being addressed in this Change Order applies to the Seward Junction Southeast portion of the project.

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Andrea Schiele 10/01/2020 11:29 AM
Form Started By:
dhaggard
Started On:
09/29/2020 04:15 PM
Final Approval Date:
10/01/2020