Commissioners Court - Regular Session
- Meeting Date:
- 02/02/2021
- Title:
- 1809-261 CR 110 Middle Change Order No. 6
- Submitted By:
- Dawn Haggard, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider and take appropriate action regarding Change Order No. 6 in the amount of $46,375.56 for CR 110 Middle (James Construction), a Road Bond project in Commissioner Pct. 4. P: 261 Funding Source: Road Bond
Background
This Change Order adds pay items to compensate the Contractor to mill and repave a portion of existing University Boulevard that was not called out to be paved in the plans. The area to be milled and repaved is located just east of the new CR 110 intersection and has not been included in any previous overlays of University Boulevard. This is existing pavement that is showing signs of deterioration. Milling is required to maintain the existing profile of University Boulevard and also maintain drainage from the pavement.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Andrea Schiele | 01/28/2021 10:24 AM |
- Form Started By:
- dhaggard
- Started On:
- 01/13/2021 11:10 AM
- Final Approval Date:
- 01/28/2021