58.
Commissioners Court - Regular Session
- Meeting Date:
- 08/31/2021
- Title:
- T3082 Southeast Loop Phase 2 Demolition Change Order No. 1
- Submitted By:
- Mayra Ramos, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 1 in the amount of ($12,682.90) for T3082 Southeast Loop Phase 2 Demolition (HCS, Inc. Commercial General Contractor) P: 463 Funding Source: Road Bond.
Background
This Change Order provides the final balancing for the overrun/underrun of Contract
quantities on the project as a result of addressing field conditions not accounted for in the
original plans.
This Change Order results in a decrease of $12,682.90 to the Contract amount, for an
adjusted Contract total of $168,235.43. The original Contract amount was $180,918.33.
As a result of this and all Change Orders to-date, $12,682.90 has been deducted from
the Contract, resulting in an 7% net decrease in the Contract cost.
quantities on the project as a result of addressing field conditions not accounted for in the
original plans.
This Change Order results in a decrease of $12,682.90 to the Contract amount, for an
adjusted Contract total of $168,235.43. The original Contract amount was $180,918.33.
As a result of this and all Change Orders to-date, $12,682.90 has been deducted from
the Contract, resulting in an 7% net decrease in the Contract cost.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 08/26/2021 10:50 AM |
- Form Started By:
- mayra.ramos
- Started On:
- 08/23/2021 03:29 PM
- Final Approval Date:
- 08/26/2021