41.
Commissioners Court - Regular Session
- Meeting Date:
- 06/07/2022
- Title:
- T2232 Hairy Man Rd Brushy Creek Rd Change Order #4 (Correction)
- Submitted By:
- Julissa Vasquez, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 4 in the amount of $0 for Project T2232 Hairy Man Rd Brushy Creek Rd (DeNucci Constructors, LLC) Funding Source: Road Bond P284.
Background
This Change Order provides the final balancing for the overruns/underruns of contract quantities on the project that are a result of addressing field conditions not accounted for in the original plans. The amount entered on the cover page of Change Order 1 was $6,004 and it should have been $6,040. The contractor has been paid correctly.
This Change Order results in a net increase of $36.00 to the Contract amount, for an adjusted Contract total of $3,526,929.95. The original Contract amount was $3,964,380.00. As a result of this and all Change Orders to-date, $437,450.05 has been deducted from the Contract, resulting in a 11.00% net decrease in the overall Contract cost. No time will be added to the Contract for this Change Order.
This Change Order results in a net increase of $36.00 to the Contract amount, for an adjusted Contract total of $3,526,929.95. The original Contract amount was $3,964,380.00. As a result of this and all Change Orders to-date, $437,450.05 has been deducted from the Contract, resulting in a 11.00% net decrease in the overall Contract cost. No time will be added to the Contract for this Change Order.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 06/02/2022 10:01 AM |
- Form Started By:
- Julissa Romero
- Started On:
- 05/31/2022 02:29 PM
- Final Approval Date:
- 06/02/2022