- 22IFB57 CR 401 Reconstruction Change Order #3 (City of Taylor Water Line)
- Submitted By:
- Julissa Vasquez, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 3 in the amount of $214,351.37 for Project 22IFB57 CR 401 Reconstruction (James Construction Group, LLC) P: 390c Funding Source: Road Bond.
Background
This Change Order revises the City of Taylor water line pipe material from ductile iron to PVC. This is necessary due to the availability of materials. Switching the pipe material to PVC was approved by the City of Taylor, everywhere except under the UPRR railroad ROW. This area is to remain per plan as ductile iron. This Change Order will allow for timely delivery of materials.
The following new items will be added by this Change Order.
This Change Order results in an increase of $214,351.37 to the Contract amount, for an adjusted Contract total of $13,315,267.83. The original Contract amount was $12,673,200.94. As a result of this and all Change Orders to-date, $642,066.89 has been added to the Contract, resulting in a 5.07% net increase to the overall Contract cost. Due to the current uncertainty in material lead times, time adjustments for this work will be deferred to a later time. Additional time will be determined once materials are on site and will only be granted after the completion of the original scope of work.
The following new items will be added by this Change Order.
| ITEM | DESCRIPTION | QUANTITY | UNIT |
| COT-WC01 | City of Taylor WL - Change from Ductile Iron to PVC Pipe | 1.00 | LS |
This Change Order results in an increase of $214,351.37 to the Contract amount, for an adjusted Contract total of $13,315,267.83. The original Contract amount was $12,673,200.94. As a result of this and all Change Orders to-date, $642,066.89 has been added to the Contract, resulting in a 5.07% net increase to the overall Contract cost. Due to the current uncertainty in material lead times, time adjustments for this work will be deferred to a later time. Additional time will be determined once materials are on site and will only be granted after the completion of the original scope of work.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 09/29/2022 10:40 AM |
- Form Started By:
- Julissa Romero
- Started On:
- 09/26/2022 07:48 AM
- Final Approval Date:
- 09/29/2022