18.
Commissioners Court - Regular Session
- Meeting Date:
- 10/25/2022
- Title:
- DIJ Construction 21IFB21 CO1 County Road Seal Coat
- Submitted For:
- Terron Evertson
- Submitted By:
- Vicky Edwards, Infrastructure
- Department:
- Infrastructure
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider and take appropriate action on Change Order No 1 to contract number 21IFB21 for DIJ Construction Inc in the amount of -$30,438.20 for County Road Seal Coat FY22. Funding source: 01.0200.0210.003599.
Background
This Change Order is a balancing Change Order. All work has been completed. Original contract amount $1,052,638.20. With the addition of this Change Order of -$30,438.20, the final contract amount will be $1,022,200.00.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 10/20/2022 11:05 AM |
- Form Started By:
- Vicky Edwards
- Started On:
- 10/20/2022 09:43 AM
- Final Approval Date:
- 10/20/2022