Skip to main content

AgendaQuick™

View Agenda Item

58.
Commissioners Court - Regular Session
Meeting Date:
02/28/2023
Title:
22IFB57 CR 401 Reconstruction Change Order #4 (City of Taylor Water Line)
Submitted By:
Julissa Vasquez, Road Bond
Department:
Road Bond
Agenda Category:
Regular Agenda Items

Information

Agenda Item

Discuss, consider, and take appropriate action regarding Change Order No. 4 in the amount of $188,826.95 for Project 22IFB57 CR 401 Reconstruction (James Construction Group, LLC) P: 390 Funding Source: Road Bond.

Background

This Change Order revises and adds additional items to the Contract for the adjustments needed to the City of Taylor water line on the north side of US 79 that conflicts with the proposed roadway and ditch cuts. This line is also being upsized to stay consistent with the proposed water line on CR 401.

This Change Order also addresses the need for an additional fire hydrant requested by the City of Taylor on the southeast side of US 79 and proposed CR 401.  The City of Taylor has agreed to reimburse Williamson County for the additional work. See attached Change Order for additional details.

This Change Order results in an increase of $188,826.95 to the Contract amount, for an adjusted Contract total of $13,504,094.78. The original Contract amount was $12,673,200.94. As a result of this and all Change Orders to-date, $830,893.84 has been added to the Contract, resulting in a 6.56% net increase to the overall Contract cost.
 

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Becky Pruitt 02/23/2023 06:13 PM
Form Started By:
Julissa Romero
Started On:
02/20/2023 08:13 AM
Final Approval Date:
02/23/2023