29.
Commissioners Court - Regular Session
Meeting Date:
03/28/2023
Title:
T3346 Southeast Loop Segment 1 Phase 1 Change Order #4 (Force Account Items)
Submitted By:
Julissa Vasquez, Road Bond
Department:
Road Bond
Agenda Category:
Regular Agenda Items

Information

Agenda Item

Discuss, consider, and take appropriate action regarding Change Order No. 4 in the amount of $156,231.96 for Project T3346 Southeast Loop Segment 1 Phase 1 (James Construction Group) P: 463 Funding Source: Road Bond.

Background

This Change Order adds several new items to the Contract that have been previously paid for under the existing Force Account line item. New items include building an access road to the interior bridge bents at the Soil Conservation Service Pond, a driveway to the new development just west of the Bridge Church, removal of an old light pole foundation and septic tank discovered after excavation began, potholing for existing utilities, and trash removal. 

Multiple items will be added by this Change Order. Please see attached Change Order.

This Change Order results in a net increase of $156,231.96 to the Contract amount, for an adjusted Contract total of $12,082,546.41. The original Contract amount was $11,526,789.09. As a result of this and all Change Orders to-date, $555,757.32 has been added to the Contract, resulting in a 4.82% net increase in the overall Contract cost.
 

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Becky Pruitt 03/23/2023 09:53 AM
Form Started By:
Julissa Romero
Started On:
03/22/2023 08:37 AM
Final Approval Date:
03/23/2023