52.
Commissioners Court - Regular Session
Meeting Date:
07/18/2023
Title:
22IFB139 FM 3349 at US 79 - Change Order #3 (Utility Sleeve)
Submitted By:
Julissa Vasquez, Road Bond
Department:
Road Bond
Agenda Category:
Regular Agenda Items

Information

Agenda Item

Discuss, consider, and take appropriate action regarding Change Order No. 3 in the amount of $195,302.81 for Project 22IFB139 FM3349 at US79 (James Construction Group) P: 332 Funding Source: Road Bond.

Background

This Change Order compensates the contractor for installing one steel utility sleeve casing, 24 inches in diameter, under FM 3349 at station 421+00. Installation of this utility was stipulated as a requirement in the purchase agreement for the project Right-of-Way at this location. Please see attached Change Order.

This Change Order results in a net increase of $195,302.81 to the Contract amount, for an adjusted Contract total of $83,143,695.35. The original Contract amount was $81,941,038.13.  As a result of this and all Change Orders to-date, $1,202,657.22 has been added to the Contract, resulting in an 1.47% net increase in the Contract cost.  No additional days will be added to or deducted from the Contract as a result of this Change Order. 
 

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Becky Pruitt 07/12/2023 12:48 PM
Form Started By:
Julissa Romero
Started On:
06/21/2023 03:49 PM
Final Approval Date:
07/12/2023