Commissioners Court - Regular Session
- Meeting Date:
- 10/17/2023
- Title:
- Old DPS Remodel (ARPA 445P-12) – GC6 – AR1 for G2 Construction
- Submitted For:
- Dale Butler
- Submitted By:
- Wendy Danzo, Facilities Management
- Department:
- Facilities Management
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider and take appropriate action on a report from G2 Construction for the Old DPS Remodel project (ARPA 445P/445A/12), First Amended and Restated Contract for Construction for a time extension of 270 days and for $702,000. Funding Source is 445P/44A/Old DPS Remodel/12.
Background
This amendment and restated agreement is to increase funds by $267,000 and add 270 days to substantial completion. Changes are required due to construction remodel issues resulting in changes to original scope. Department point of contact is Thomas Crockett, Facilities Management Project Manager. Funding for this project is 445P/445A Old DPS Remodel/12.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Hal Hawes | Shannon Francis | 10/12/2023 11:48 AM |
| County Judge Exec Asst. | Becky Pruitt | 10/12/2023 02:11 PM |
- Form Started By:
- wendy.danzoy
- Started On:
- 10/11/2023 12:29 PM
- Final Approval Date:
- 10/12/2023