42.
Commissioners Court - Regular Session
- Meeting Date:
- 10/31/2023
- Title:
- 23IFB34 CR 307 Reconstruction - Change Order 1 (Work Zone Striping)
- Submitted By:
- Julissa Vasquez, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 1 in the amount of $10,447.50 for Project 23IFB34 CR 307 Reconstruction (Joe Bland Construction) P: 394 Funding Source: Road Bond.
Background
This Change Order compensates the Contractor for installing work zone pavement markings on CR 307, which were not included in the bid tabs. The work zone pavement markings were added for additional safety measures due to the new school being opened. Please see attached Change Order for additional details.
This Change Order results in a net increase of $10,447.50 to the Contract amount, for an adjusted Contract total of $2,807,280.30. The original Contract amount was $2,796,832.80. As a result of this and all Change Orders to-date, $10,447.50 has been added to the Contract, resulting in a 0.37% net increase in the overall Contract cost. As a result of this Change Order, zero (0) days will be added to the contract.
This Change Order results in a net increase of $10,447.50 to the Contract amount, for an adjusted Contract total of $2,807,280.30. The original Contract amount was $2,796,832.80. As a result of this and all Change Orders to-date, $10,447.50 has been added to the Contract, resulting in a 0.37% net increase in the overall Contract cost. As a result of this Change Order, zero (0) days will be added to the contract.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 10/26/2023 10:50 AM |
- Form Started By:
- Julissa Romero
- Started On:
- 10/25/2023 02:43 PM
- Final Approval Date:
- 10/26/2023