Skip to main content

AgendaQuick™

View Agenda Item

31.
Commissioners Court - Regular Session
Meeting Date:
12/05/2023
Title:
LE Drop Center (445P/445A/2.1) - Change Order #2
Submitted For:
Dale Butler
Submitted By:
Christy Matoska, Facilities Management
Department:
Facilities Management
Agenda Category:
Consent

Information

Agenda Item

Discuss, consider and take appropriate action on a change order from Chasco Constructors, Ltd., LLP for an increase of $6,267.50. The new Contract Sum will be $284,732.50. The Contract Time will be increased by thirty-one (31) days.

Background

This change order is for Chasco Constructors, Ltd., LLP to increase the Contract Sum by $6,267.50, with the new Contract Sum of $284,732.50. In addition, increase the substantial completion date by 31 days, with a new substantial completion date of 12/31/23.

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Becky Pruitt 11/29/2023 08:57 AM
Form Started By:
Christy Matoska
Started On:
11/28/2023 08:39 AM
Final Approval Date:
11/29/2023