- Title:
- 23IFB6 - CR 404 at FM973 Change Order # 2 (Balancing)
- Submitted By:
- Julissa Vasquez, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 2 in the amount of ($102,266.57) for Project 23IFB6 CR 404 at FM 973 (Jordan Foster) P: 390 Funding Source: Road Bond.
Background
This Change Order provides the balancing for the overruns/underruns of Contract quantities on the project that are a result of addressing field conditions not accounted for in the original plans. This Change Order also adds advanced flashing beacons and signs to improve safety along FM 973. See attached Change Order for details.
This Change Order results in a net decrease of $102,266.57 to the Contract amount, for an adjusted Contract total of $4,814,077.33. The original Contract amount was $4,622,143.93. As a result of this and all Change Orders to-date, $191,933.40 has been added to the Contract, resulting in a 4.15% net increase in the overall Contract cost. As a result of this Change Order, zero (0) days will be added to the Contract.
This Change Order results in a net decrease of $102,266.57 to the Contract amount, for an adjusted Contract total of $4,814,077.33. The original Contract amount was $4,622,143.93. As a result of this and all Change Orders to-date, $191,933.40 has been added to the Contract, resulting in a 4.15% net increase in the overall Contract cost. As a result of this Change Order, zero (0) days will be added to the Contract.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 02/08/2024 09:17 AM |
- Form Started By:
- Julissa Romero
- Started On:
- 02/07/2024 07:14 AM
- Final Approval Date:
- 02/08/2024