44.
Commissioners Court - Regular Session
- Meeting Date:
- 04/16/2024
- Title:
- 22IFB139 FM 3349 at US 79 - Change Order #13 (Existing Road Repairs)
- Submitted By:
- Julissa Vasquez, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 13 in the amount of $82,301.65 for Project 22IFB139 FM3349 at US79 (James Construction) P: 332 Funding Source: Road Bond.
Background
This Change Order provides compensation to the Contractor for performing pavement repairs, within the project limits, on the existing FM 3349 roadway. The repairs include fixing ruts and cracks and repairing a crash cushion and MBGF damaged by the public. This Change Order also adds new items to install additional small signs to improve safety on the CR 101 ( Jughandle Road), pay for off-duty police officers, and locating an existing utility line. Please see the attached Change Order for additional details.
This Change Order results in a net increase of $82,301.65 to the Contract amount, for an adjusted Contract total of $83,902,545.10. The original Contract amount was $81,941,038.13. As a result of this and all Change Orders to-date, $1,961,506.97 has been added to the Contract, resulting in an 2.39% net increase in the Contract cost. No additional days will be added to or deducted from the Contract as a result of this Change Order.
This Change Order results in a net increase of $82,301.65 to the Contract amount, for an adjusted Contract total of $83,902,545.10. The original Contract amount was $81,941,038.13. As a result of this and all Change Orders to-date, $1,961,506.97 has been added to the Contract, resulting in an 2.39% net increase in the Contract cost. No additional days will be added to or deducted from the Contract as a result of this Change Order.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 04/11/2024 11:23 AM |
- Form Started By:
- Julissa Romero
- Started On:
- 04/10/2024 11:26 AM
- Final Approval Date:
- 04/11/2024