36.
Commissioners Court - Regular Session
- Meeting Date:
- 05/21/2024
- Title:
- CR 129 – Standard Utility Agreement with Manville Water Supply Corporation
- Submitted By:
- Julissa Vasquez, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding the Utility Agreement with Manville Water for utility relocations on the CR 129 Project, a Road Bond Project in Commissioner Precinct 4. P:375.
Background
Manville water has existing facilities in conflict with the CR 129 Project. The Standard Utility Agreement for the relocations is for a total amount of $101,624.56. Manville Water is 100% eligible for reimbursement. The total anticipated reimbursement to Manville Water by the County is $101,624.56 (100% of $101,624.56).
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 05/16/2024 09:07 AM |
- Form Started By:
- Julissa Romero
- Started On:
- 05/15/2024 03:36 PM
- Final Approval Date:
- 05/16/2024