34.
Commissioners Court - Regular Session
- Meeting Date:
- 07/02/2024
- Title:
- 23IFB67 Corridor C - SH 29 Bypass - Change Order #2 (Jonah Water Line Meter)
- Submitted By:
- Julissa Vasquez, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 2 in the amount of $9,568.50 for Project 23IFB67 Corridor C - SH 29 (Capital Excavation) P: 459 Funding Source: Road Bond.
Background
This Change Order compensates the Contractor for additional work related to maintaining an existing Jonah water service that was identified during the relocation of the new Jonah water line along CR 106 but was not accounted for in the plans. Per RFI 2, Jonah stated to maintain the existing service and provided revised plan sheets and additional quantities for this work.
This Change Order results in an increase of $9,568.50 to the Contract amount, for an adjusted Contract total of $30,556,617.53. The original Contract amount was $30,540,848.03. As a result of this and previous Change Orders, $15,769.50 has been added to the Contract, resulting in a .05% increase in the Contract cost. As a result of this Change Order, zero (0) days will be added to the Contract.
This Change Order results in an increase of $9,568.50 to the Contract amount, for an adjusted Contract total of $30,556,617.53. The original Contract amount was $30,540,848.03. As a result of this and previous Change Orders, $15,769.50 has been added to the Contract, resulting in a .05% increase in the Contract cost. As a result of this Change Order, zero (0) days will be added to the Contract.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 06/27/2024 12:57 PM |
- Form Started By:
- Julissa Romero
- Started On:
- 06/19/2024 08:36 AM
- Final Approval Date:
- 06/27/2024