35.
Commissioners Court - Regular Session
- Meeting Date:
- 07/30/2024
- Title:
- Final plat for the Rancho Del Cielo Phase 3 subdivision – Pct 4
- Submitted For:
- Adam Boatright
- Submitted By:
- Adam Boatright, Infrastructure
- Department:
- Infrastructure
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider and take appropriate action on approval of the final plat for the Rancho Del Cielo Phase 3 subdivision – Precinct 4.
Background
This is the next phase of the Rancho Del Cielo development. It consists of 186 single family lots, 1 open space/drainage lot, and 4,970 feet of new public roads. Roadway and drainage construction are not yet complete but a financial security in the amount of $1,410,974.45 has been posted with the County to cover the cost of the remaining construction.
Timeline
2024-04-16 – initial submittal of the final plat
2024-05-15 – 1st review complete with comments
2024-06-07 – 2nd submittal of final plat
2024-06-20 – 2nd review complete with comments clear
2024-06-24 – receipt of financial security for the remaining construction
2024-07-23 – receipt of final plat with signatures
2024-07-25 – final plat placed on the July 30, 2024 Commissioners Court agenda for consideration
Timeline
2024-04-16 – initial submittal of the final plat
2024-05-15 – 1st review complete with comments
2024-06-07 – 2nd submittal of final plat
2024-06-20 – 2nd review complete with comments clear
2024-06-24 – receipt of financial security for the remaining construction
2024-07-23 – receipt of final plat with signatures
2024-07-25 – final plat placed on the July 30, 2024 Commissioners Court agenda for consideration
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 07/25/2024 11:51 AM |
- Form Started By:
- Adam Boatright
- Started On:
- 07/25/2024 11:37 AM
- Final Approval Date:
- 07/25/2024