- 24IFB15 Liberty Hill Bypass - Change Order #4 (Relocate Water Line)
- Submitted By:
- Julissa Vasquez, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 4 in the amount of $14,900.00 for Project 24IFB15 Liberty Hill Bypass (Chasco Constructors) P: 343 Funding Source: Road Bond.
Background
This Change Order compensates the Contractor for relocating an existing water line to maintain service to the remainder property across the ROW that is used as pasture.
This Change Order results in a net increase of $14,900.00 to the Contract amount, for an adjusted Contract total of $14,444,811.00. The original Contract amount was $14,149,449.00. As a result of this and all Change Orders to-date, $295,362.00 has been added to the Contract, resulting in a 2.09% net increase in the Contract cost. No additional days will be added to or deducted from the Contract as a result of this Change Order.
This Change Order results in a net increase of $14,900.00 to the Contract amount, for an adjusted Contract total of $14,444,811.00. The original Contract amount was $14,149,449.00. As a result of this and all Change Orders to-date, $295,362.00 has been added to the Contract, resulting in a 2.09% net increase in the Contract cost. No additional days will be added to or deducted from the Contract as a result of this Change Order.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Andrea Schiele | 03/06/2025 12:03 PM |
- Form Started By:
- Julissa Romero
- Started On:
- 03/05/2025 06:53 AM
- Final Approval Date:
- 03/06/2025