Skip to main content

AgendaQuick™

View Agenda Item

48.
Commissioners Court - Regular Session
Meeting Date:
05/06/2025
Title:
CJC North Roof Replacement - RYCARS
Submitted For:
Dale Butler
Submitted By:
Christy Matoska, Facilities Management
Department:
Facilities Management
Agenda Category:
Regular Agenda Items

Information

Agenda Item

Receive and acknowledge approval of Change Order No.1 from RYCARS Construction, LLC for the Justice Center Roof Replacement in the amount of $14,356.00 and to extend time for completion of the roof installation, which was approved by Williamson County Project Manager, Thomas Crockett, pursuant to the Commissioners Court's prior delegation of change order approval authority pursuant to Loc. Gov't Code Sec. 262.031.

Background

The Change Order No. 1 is made to compensate the contractor, RYCARS Construction, LLC. for overflow drains - install retrofit drains on Side B, capping off existing overflow drains on Side A roof. This Change Order results in a net increase of $14,356.00. The original Contract amount was $650,715.00. As a result of this Change Order, the net increase is 2.2% in the Contract cost with a new contract sum of $665,071.00. Williamson County Facilities Project Manager, Thomas Crockett was delegated change order approval authority for this project on January 23, 2024, by the Commissioners Court pursuant to Loc. Gov't Code Sec. 262.031. This item is to acknowledge such approval and record same into the minutes of the Commissioners Court.

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Hal Hawes Hal Hawes 04/29/2025 09:37 AM
Facilities Management (Originator) Christy Matoska 04/29/2025 10:00 AM
Hal Hawes Hal Hawes 04/29/2025 01:07 PM
County Judge Exec Asst. Andrea Schiele 05/01/2025 02:35 PM
Form Started By:
Christy Matoska
Started On:
04/29/2025 09:03 AM
Final Approval Date:
05/01/2025