54.
Commissioners Court - Regular Session
- Meeting Date:
- 05/06/2025
- Title:
- Red Bud SLG PSA Amendment No. 1
- Submitted By:
- Marie Walters, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action on Contract Amendment No. 1 to the Red Bud Lane contract executed March 19, 2024, between Williamson County and Seiler Lankes Group, LLC relating to the 2023 Road Bond Program. Project: P657 Fund Source: Road Bonds
Background
This Contract Amendment No. 1 increases the compensation cap by $290,000.00 from $400,000.00 to $690,000.00 to allow for the execution of Supplemental No. 1 to Work Authorization No. 1.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Andrea Schiele | 05/01/2025 11:36 AM |
- Form Started By:
- Marie Walters
- Started On:
- 04/30/2025 06:52 PM
- Final Approval Date:
- 05/01/2025