Discuss, consider, and take appropriate action regarding a Utility Reimbursement Agreement with Pedernales Electric Cooperative (PEC) regarding utility adjustments on Seward Junction Southeast, a Road Bond Project in Commissioner Pct. 2.
Background
PEC has existing facilities in conflict with the Seward Junction Southeast Project. PEC is 100% eligible for reimbursement. The total anticipated reimbursement to PEC by the County is $78,572.27 for 11 pole removals, 13 new electric pole installations, the associated electric conductor and ancillaries. The total eligible costs do not include any betterments, because those costs are paid for by the Utility Owner.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
- Seward Junction Southeast PEC Utility Reimbursement Agmt
- Utility Reimbursement Agreement with Pedernales for Seward Junction SE
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Wendy Coco | 12/01/2016 10:50 AM |
- Form Started By:
- dhaggard
- Started On:
- 11/30/2016 11:02 AM
- Final Approval Date:
- 12/01/2016