20.
Commissioners Court - Regular Session
- Meeting Date:
- 02/28/2017
- Title:
- 15IFB102 CR 245 Change Order No. 2
- Submitted By:
- Dawn Haggard, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 2 in the amount of -$35,569.89 for CR 245, a Road Bond Project in Commissioner Pct. 3.
Background
This Change Order provides the final balancing for the overrun/underrun of Contract quantities on the project as a result of addressing field conditions not accounted for in the original plans. It also adds Item 169-2001 Soil Retention Blanket to the contract which replaces the 3” Erosion Control Compost due to the unavailability of the compost material. The underruns documented by this Change Order result in a cost savings for the County. Ten (10) days will be added to the Contract on this Change Order for the lead time for the fabrication of the pressure release valve vault for the City of Georgetown waterline added by Change Order #1.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Wendy Coco | 02/23/2017 11:47 AM |
- Form Started By:
- dhaggard
- Started On:
- 02/23/2017 10:34 AM
- Final Approval Date:
- 02/23/2017