50.
Commissioners Court - Regular Session
Meeting Date:
11/14/2017
Title:
Awarding IFB 1708 187 Relocation of Wilco Regional Raw Water Line
Submitted For:
Randy Barker
Submitted By:
Thomas Skiles, Purchasing
Department:
Purchasing
Agenda Category:
Regular Agenda Items

Information

Agenda Item

Discuss, consider, and take appropriate action on awarding IFB # 1708-187, Relocation of Williamson County Regional Raw Water Line, contingent upon execution of the Interlocal Agreement with all parties, to the lowest responsive bidder Santa Clara Construction.

Background

The bids have been reviewed and the apparent low bid (Santa Clara Construction) was found to be responsive,
mathematically correct, and materially balanced.

Following is a summary of the bid totals:

1. Santa Clara Construction $1,232,539.10
2. Austin Underground $1,297,764.40
3. CRU, Ltd $1,324,701.50
4. MA Smith Contracting $1,387,325.40
5. Whitestone Civil Construction $1,514,387.00
6. Skyblue Utilities $1,735,488.21
7. C.C. Carlton Industries $1,821,004.25

The Contractor’s low bid is $207,267.85 below the Engineer’s Estimate, a cost saving of 14.4%.
The bidding was competitive with the lowest three bidders being within 10% of each other.
In addition to meeting the bid qualifications subject to being low bidder, Santa Clara
Construction have successfully completed past projects that focus on specialized pipe work.

Based on the experience of the Contractor and the positive reviews of the references contacted, HNTB concurs with the recommendation of the Design Engineer, Cobb Fendley, to award the Relocation of the Williamson County Regional Raw Water Line contract to Santa Clara
Construction in the contract amount of $1,232,539.10.

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Rebecca Clemons 11/09/2017 11:31 AM
Form Started By:
blake.skiles
Started On:
11/08/2017 01:01 PM
Final Approval Date:
11/09/2017