13.
Commissioners Court - Regular Session
- Meeting Date:
- 12/12/2017
- Title:
- Sheriff's Office Training Center, P323 - Change Order 36
- Submitted By:
- Gina Wrehsnig, Infrastructure
- Department:
- Infrastructure
- Division:
- Building Maintenance
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider and take appropriate action on accepting and approving a report on the Sheriff’s Office Training Center Project; Change Order #36 in the amount of $8,620.10 for additional HVAC and fixture work at the SWAT Locker area of the building, which was executed by Gary Wilson, Director of Williamson County Facilities, pursuant to the previous grant of authority under Section 262.031 of the Local Government Code. This change order is being funded by the Construction Managers Contingency.
Background
On September 6, 2016, the Williamson County Commissioners Court granted Gary Wilson, Director of Williamson County Facilities, with general authority to approve change orders for the Agreement for Construction Services with American Constructors, Inc. in relation to the Williamson County Sheriff’s Office Training Center Project for any increase in costs up to a total maximum amount of $30,000.00 in accordance with Section 262.031 of the Local Government Code – Changes in Plans and Specifications. This report is being provided for purposes of notifying the court of such change order and to place it in the minutes of the Commissioners Court.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Wendy Coco | 12/07/2017 09:15 AM |
- Form Started By:
- Gina Wrehsnig
- Started On:
- 12/07/2017 07:46 AM
- Final Approval Date:
- 12/07/2017