Skip to main content

AgendaQuick™

View Agenda Item

14.
Commissioners Court - Regular Session
Meeting Date:
01/23/2018
Title:
1603-064 Arterial H Change Order No. 2
Submitted By:
Dawn Haggard, Road Bond
Department:
Road Bond
Agenda Category:
Regular Agenda Items

Information

Agenda Item

Discuss, consider, and take appropriate action regarding Change Order No. 2 in the amount of $58,143.87 for Arterial H, a Road Bond Project in Commissioner Pct. 3.  Project: P276. Funding Source: Road Bonds.

Background

This Change Order is for the following: the addition of soil retention blankets to the contract to minimize erosion and aid in vegetation establishment on the slopes along the roadway; the addition of various items of work shown on the original plans but not included in the summary of quantities; the modification of backless style curb inlets to standard curb inlets to eliminate the need for additional pedestrian handrail; and the elimination of lime treated subgrade items in the contract.  The subgrade material was tested throughout the project to confirm that the lime treated subgrade was not needed.  An item for subgrade prep was added to the contract for the work that the Contractor performed to get the subgrade ready for flexible base.  The Change Order also includes the addition of 120 Calendar Days to the Contract time.  The Contractor delayed the start of construction on Culvert A and the subgrade adjacent to the pond to allow the pond contractor to complete construction of the detention pond. 

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Wendy Coco 01/18/2018 09:54 AM
Form Started By:
dhaggard
Started On:
01/17/2018 02:35 PM
Final Approval Date:
01/18/2018