- Title:
- 1608-108 RM 620 Phase 2 Change Order No. 6
- Submitted By:
- Dawn Haggard, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 6 (Cox Commercial Construction) in the amount of -$247,076.96 for RM 620 Phase 2, a Road Bond Project in Commissioner Pct. 1.
Project: P235 Funding: Road Bond
Project: P235 Funding: Road Bond
Background
This Change Order provides for the final balancing for the overrun/underrun of Contract quantities on the project due to addressing field conditions not accounted for in the original plans. Additional time was necessary for extra scope at the Oaklands Drive intersection for drainage and median improvements. Additional time was also granted for delays due to conflicts with existing utilities and for non-working days that were previously charged. The project encountered extreme wet weather conditions that could not have been anticipated by the Contractor and TxDOT requested limited work on various holidays during the construction of the project.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Andrea Schiele | 04/04/2019 10:18 AM |
- Form Started By:
- dhaggard
- Started On:
- 04/02/2019 01:51 PM
- Final Approval Date:
- 04/04/2019