Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 1 in the amount of $66,291.83 for CR 110 Middle(James Construction), a Road Bond project in Commissioner Pct. 4.
Project: P261 Funding: Road Bond
Project: P261 Funding: Road Bond
Background
This Change Order revises items and quantities related to the traffic signals, adds items for temporary sediment control fencing (install and remove) and credits the contract for materials (6' x 4' box culvert) furnished by the County. The Type D signal poles replace the Type B signal poles originally called out in the plans. Additionally, street name signs will be added to the signals at Limmer Loop. Item 681-6001 Temporary Traffic Signals is added to the contract to compensate the Contractor to maintain the traffic signals during the construction of the project. This item was not originally included in the contract. This Change Order adds item 506-6038 Temporary Sediment Control Fence (Install) and Item 506-6039 Temporary Sediment Control (remove) to the contract to reduce erosion during construction.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Andrea Schiele | 10/03/2019 10:27 AM |
- Form Started By:
- dhaggard
- Started On:
- 10/02/2019 11:49 AM
- Final Approval Date:
- 10/03/2019