1809-261 CR 110 Middle Change Order No. 2
Submitted By:
Dawn Haggard, Road Bond
Department:
Road Bond
Agenda Category:
Consent

Information

Agenda Item

Discuss, consider, and take appropriate action regarding Change Order No. 2 in the amount of $31,881.14 for CR 110 Middle (James Construction Group) , a Road Bond project in Commissioner Pct. 4. 
P:261  Funding Source: Road Bond

Background

This Change Order adds excavation and grading for the ditch line along the north side of Limmer Loop at CR 110. The construction of the ditch was originally included in the previous CR 110 South contract but was not completed due to a utility conflict. The underground utility was recently relocated, and the ditch excavation was added to the current project at the request of the County.

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Andrea Schiele 12/12/2019 10:09 AM
Form Started By:
dhaggard
Started On:
12/10/2019 02:04 PM
Final Approval Date:
12/12/2019