47.
Commissioners Court - Regular Session
Meeting Date:
01/07/2020
Title:
1708-186 CR 119 Change Order No. 1
Submitted By:
Dawn Haggard, Road Bond
Department:
Road Bond
Agenda Category:
Consent

Information

Agenda Item

Discuss, consider, and take appropriate action regarding Change Order No. 1 in the amount of -$61,412.38 for CR 119 (Joe Bland Construction), a Road Bond project in Commissioner Pct. 4.
P:214   Funding: Road Bond

Background

This Change Order provides the final balancing for the overrun/underrun of contract quantities as a result of addressing field conditions not accounted for in the original plans.  This Change Order corrects the quantity for the channel excavation item, corrects quantities for paving in the original contract, adds driveways to maintain access to properties along the project, and revises vegetation establishment items. This Change Order also adds milling, paving, and restriping for a left turn lane on Chandler Road, as requested by the County. The plan quantities for various paving items and channel excavation under the Cottonwood Creek Bridge were corrected after construction began. The County also agreed to add three (3) driveways to different properties that were divided by the right-of-way acquisition for the project north of Limmer Loop on the west side. Two driveways are located on CR 119, between Limmer Loop and CR 118. The third driveway on CR 119 is north of CR 118. These driveways were requested by the property owners.

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Andrea Schiele 01/01/2020 09:43 PM
Form Started By:
dhaggard
Started On:
12/31/2019 01:27 PM
Final Approval Date:
01/01/2020