Commissioners Court - Regular Session
- Meeting Date:
- 04/07/2020
- Title:
- 1803-219 - Southwest Bypass Segment 2 Change Order No 3
- Submitted By:
- Dawn Haggard, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 3 in the amount of $48,061.86 for Southwest Bypass Segment 2, a Road Bond project in Commissioner Pct. 3.
P: 243 Funding: Road Bond
P: 243 Funding: Road Bond
Background
This Change Order pays for the tree protection and trimming services required prior to power being established at the signals at the intersection of Southwest Bypass and RM 2243. Williamson County has requested that the Contractor make the signal fully functional and put them into operation. To do this, the City of Georgetown requires an arborist be on site to determine which trees would need protective fencing, which would need pruning, and which may need removal to allow the power to be installed to the signal.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Andrea Schiele | 04/02/2020 11:53 AM |
- Form Started By:
- dhaggard
- Started On:
- 04/01/2020 03:15 PM
- Final Approval Date:
- 04/02/2020